Soil remediation on a former fitting production facility in Magdeburg

Back to the future

On the grounds of a former fitting production facility in Magdeburg, the Bauer Resources team prepared the soil for a successful new beginning. Approximately 5,600 m3 of soil were excavated and 3,350 m3 of contaminated material were replaced to a depth of 9 m. At the end of the large-scale drilling work, roughly 20,000 tons of contaminant remained, which were transported to a soil treatment center in gas-tight and impermeable containers. Furthermore, a water treatment plant was used to clean roughly 110 m3 of polluted groundwater. Business as usual, but extremely hard work for our team: this was due to the clayey soil as well as the necessary occupational safety measures in the black zone. 

Facts about the project
Company :

BAUER Resources GmbH, Bauer Umwelt Division

Location :

Liebknechtstr. 71, 39108 Magdeburg

Period :

July to November 2022

Services :

Dismantling, soil remediation, groundwater treatment, disposal

Contaminants :

Gasoline, diesel, heating oil (TPH), BTEX, CHC / halogenated VOC

Rehabilitation methods :

Replacement boring, Pump & Treat

Press release :

Replacement boring with prospects

Replacement boring by Bauer Resources in Magdeburg
Replacement boring by Bauer Resources in Magdeburg
The team from Bauer Resources is equipped with special protective suits during drilling of large-scale boreholes on the site of Magdeburg fitting production facility
The team from Bauer Resources is equipped with special protective suits during drilling of large-scale boreholes on the site of Magdeburg fitting production facility
Soil replacement by Bauer Resources at former fitting production facility in Magdeburg
Soil replacement by Bauer Resources at former fitting production facility in Magdeburg
The Bauer Resources team worked in the black zone at the former fitting production facility in Magdeburg

Due to the degree of contamination, work was carried out in the black zone. This requires lots of experience and absolute safety for the operator and the environment.”

Lutz Hupfer
Site Manager

Time for the next project?

Get in touch with us.

Holm Uhlig
Sales

Region East