Demolition in the heart of Munich

Precision work in the tightest of spaces

In the heart of Munich, the specialists from Bauer Resources once again demonstrated that cramped conditions and bustling activity all around the construction site have long been matters of routine. They completely gutted and demolished a dilapidated building from the 1950s in just a few weeks, relying on sharp intuition and under the strictest safety requirements – approximately 3000 t of demolition material were generated and removed in the process. Then it was time to dig deep, excavating a 1,600 m3 excavation pit. All in all, this was an impressive example of high-precision work.

Facts about the project
Company :

BAUER Resources GmbH, Bauer Umwelt Division

Location :

St.-Anna-Straße 25, 80538 Munich

Period :

May 2021 to December 2022

Services :

Dismantling, disposal, retaining structure, excavation pit construction

Press release :

The future starts with demolition...

In order to display the video on the US platform YouTube, we need your consent to the associated data processing, as described in our data protection declaration. Agree and view external content

Bauer Resources employee demolished a residential building in Munich using a long reach excavator

The demolition of a four-story building in the tightest of spaces is not an easy matter. Every movement has to be spot on.”