The iCampus project in Munich’s Werksviertel district is an impressive example of how a contaminated historical industrial site can be transformed into a highly modern residential/commercial development. Bauer Resources was responsible for the complete brownfield remediation of the site with an area of 22,500 m2: starting with the gutting and demolition of the existing buildings all the way to the subsequent rehabilitation work and soil excavation. A total of around 50,000 m3 of concrete was broken up and almost 125,000 m3 of ground excavated and disposed of. The challenges: a protected monument, more asbestos than was expected along with tight spatial conditions and a high volume of waste material in an urban area. But the project ran on schedule despite all the challenges thanks to excellent cooperation within our team.
BAUER Resources GmbH, Bauer Umwelt Division
Friedenstraße 22B, 81671 Munich
May 2019 to May 2021
iCampus
Dismantling, building rehabilitation, soil remediation, excavation pits, dismantling
Asbestos, asphalt, gasoline, diesel, heating oil (TPH), synthetic vitreous fibers (SVF), PAH, tar oil / tar
Contaminated sites adé, iCampus olé