Excavation pit construction on a former military site in Frankfurt am Main

Efficient, precise, turnkey

What can you do if a 15,000 m2 excavation pit needs to be constructed in an extremely short time? Then everything has to mesh properly and lots of work steps have to be carried out at the same time. This was the case on a former military airport in Frankfurt am Main: During the Park Trio project there, our team demonstrated what can be achieved when everyone pulls together. Up to a depth of 5 m, roughly 55,000 t of material was excavated – a wide range from unpolluted, undisturbed soil all the way to highly polluted material in some places – and brought to suitable disposal locations in around 4,000 truck loads. In addition, a dewatering system was installed including a groundwater treatment plant, and Bauer Spezialtiefbau carried out safeguarding and soil improvement work. Starting in 2027, the Rebstock site will begin its new future: in part as a residential quarter, and also as an educational site. 

Facts about the project
Company :

BAUER Resources GmbH, Bauer Umwelt Division

Location :

Angelika-Machinek-Straße, 60486 Frankfurt am Main

Project name :

Park Trio

Project partner :

BAUER Spezialtiefbau GmbH

Period :

April 2022 to January 2023

Services :

Excavation pits, soil improvement, retaining structure, dewatering

Press release :

From excavating soil to constructing the excavation pit

Bauer Resources performing soil excavation on a former military site in Frankfurt am Main
Bauer Resources performing soil excavation on a former military site in Frankfurt am Main
Bauer Resources constructed a turnkey excavation pit including sheet pile walls at the Rebstock site in Frankfurt am Main
Bauer Resources constructed a turnkey excavation pit including sheet pile walls at the Rebstock site in Frankfurt am Main
Site Manager Raphael Werner completed the excavation pit at the Rebstock site in Frankfurt in record time

Constructing a 15,000 m2 excavation pit in record-breaking time is a considerable feat – particularly if a lot of polluted soil needs to be moved.” 

Raphael Werner
Site Manager